Working Group #8 — Integration Testing

28 Jan 2026, 10:0045m 0sPASTE
Complete

Speakers

Marcus Webb

900 words·9 segments
75%

Raj Mehta

800 words·8 segments
72%

Tom Briggs

500 words·5 segments
50%
Raj Mehta

Order sync tested 500 orders, all within 30 seconds. Invoice sync has up to 3 minutes latency from SAP batch processing.

Tom Briggs

Full 44K migration run over Christmas was clean. All records validated. Ready for production migration.

Marcus Webb

Plan production migration for second week of February.

Deferral

Invoice sync 3-minute latency to be validated with David Kim before accepting

SAP batch processing causes delay, improvement over current 24-hour batch

Raj Mehta10:20
Confidence
85%
Agreement

Production data migration scheduled for second week of February

Clean dataset needed in Dynamics before training begins

Marcus Webb10:35
Confidence
90%