Project Board #2 — December Status Review

12 Dec 2025, 10:0060m 0sPASTE
Complete

Speakers

Sarah Chen

1100 words·11 segments
82%

Marcus Webb

900 words·9 segments
75%

David Kim

600 words·6 segments
55%

Lisa Patel

500 words·5 segments
48%
Marcus Webb

Amber-green status. Good progress on data migration. SAP integration about one week behind but within buffer.

David Kim

Tracking at about 110K spent against 450K. On plan. Logic Apps decision saved us versus MuleSoft.

Lisa Patel

Manchester team has concerns about losing custom reporting. Proposed hands-on workshops in January.

Sarah Chen

Lisa, make sure Manchester gets extra attention. We cannot afford user resistance derailing the rollout.

Marcus Webb

I would not recommend bringing go-live forward. We need the full UAT window.

Action

Lisa Patel to run hands-on workshops for Manchester sales team in January

Address concerns about losing custom reporting in legacy CRM

Lisa Patel10:35
Confidence
88%
Rejection

Proposal to bring go-live date forward rejected — full UAT window required

Marcus Webb advised maintaining Q3 2026 target

Marcus Webb10:45
Confidence
90%