CRM Migration Kickoff
Speakers
Sarah Chen
Marcus Webb
Lisa Patel
David Kim
Run data cleansing sprint before migration begins
Approximately 15% of 52,000 records have incomplete fields that need cleansing before migration to Dynamics 365
Implement role-based training modules
Training will be tailored per role: sales reps, support agents, and managers rather than generic webinar
Provide detailed cost breakdown by end of February
David Kim requires cost breakdown and monthly burn reports to track budget spend against the 450K cap
Data migration mapping document draft in three weeks
Marcus to produce first draft, Lisa team to validate field mappings within one week of receiving
Assess SAP middleware requirement within two weeks
SAP integration may need custom middleware depending on data format compatibility — flag as potential cost risk